Crane for Assembling and Dismantling Tower Cranes: Complete Guide & Who Should Do It

Mobile crane 50 ton SANY STC500 lifting komponen mast section tower crane erection

Whenever you see a tower crane looming high over a Jakarta building project — whether it's a 30-story apartment in Kemang, an office building in Sudirman, or a mixed-use area in PIK — there is one question that is rarely thought of:

Who installed that crane over there?

The answer: mobile crane. And the process of assembling and dismantling it is one of the most complex, riskiest, and most experience-demanding lifting jobs in the entire construction industry.

At ASANINDO, we quite often handle tower crane assembling and dismantling work. We wrote this article from direct field experience — not from a textbook.


What is a Tower Crane and Why Does It Always Need a Mobile Crane?

Tower crane berdiri di proyek gedung bertingkat Jakarta dengan pondasi cor atau counterweight

Tower cranes can soar dozens of meters high — but before they can operate, each of their components must be lifted into position by a mobile crane from below.

Tower crane (TC) is a type of crane installed vertically by anchoring the foundation into the ground — either through cast-in-place concrete foundation (anchor bolts embedded during basement floor pouring) as well as using counterweightas a counterweight at the bottom.

Unlike mobile cranes which can move on their own, tower cranes are a type of permanently installed at one pointthroughout the project. Precisely because of that, it is very effective for:

  • The ongoing multi-story building project months to years
  • The location that very narrow where the mobile crane does not have room to maneuver every day
  • Jobs that require ultra-long range radius and consistent

A tower crane can reach the entire project area from a single central point — an efficiency that mobile cranes cannot match for large-scale, long-term projects.

But there is one interesting paradox:

The tower crane, which is responsible for lifting everything on the project, cannot install itself.

Each tower crane component must be brought to the site in a disassembled condition, then lifted and assembled one by one by a mobile crane. And when the project is finished, the entire process must be reversed — dismantled by a mobile crane from top to bottom.

This is what makes this job both unique and risky.


Main Components of a Tower Crane to Understand

Komponen tower crane mast jib counterweight di tanah sebelum proses erection assembling

Tower crane components can reach lengths of over ten meters and weigh over ten tons — all of which must be lifted to heights by a mobile crane one by one.

Before discussing the process, it is important to understand the main parts of the tower crane because each component has a specific handling sequence:

Component Function Typical Weight
Base Frame / Foundation Tower crane foundation, embedded or anchored to the floor 2–8 tons
Mast Section “Mast” vertical tower crane, installed stacked 1–3 ton per section
Slewing Unit Rotary mechanism at the top of the mast 3-6 tons
Operator Cabin Where the TC operator works 1–2 ton
Jib (Horizontal Boom) The horizontal arm that lifts the load 5–15 ton
Counter-Jib Counterbalance arm on the opposite side of the jib 3–8 ton
Counterweight Concrete ballast at the end of the counter-jib 10–20+ ton total
Hoist & Trolley Pulley and hoist system 1–3 ton

The total weight of a complete tower crane unit can reach 40–80 tons or more — spread across dozens of components that must be lifted one by one to an increasing height each time a new mast section is added.


Tower Crane Dismantling Process: Step by Step

Mobile crane 50 ton SANY STC500 lifting komponen mast section tower crane erection

Lifting a tower crane mast section to height requires a mobile crane with both a large capacity AND a long boom — both must be calculated simultaneously.

Dismantling of a tower crane is usually done after the project is completed or when the TC is no longer needed. This is the reverse of the erection process—but similarly requires precision and a strict sequence.

Why does dismantling start from the top? Because tower cranes are balanced by design, if the dismantling sequence is wrong — for example, trying to remove a mast section before the jib and counterweight are lifted — the entire structure can lose its balance with very serious consequences.


Step 1: Preparation and Planning Before Work

Before a single bolt is removed, the team must prepare:

  • Lifting plan for each component — weight, lifting point, mobile crane radius, and the required capacity for that configuration
  • Mobile crane positioning — the crane must be able to reach all TC components from a safe and stable position
  • Briefing the entire team — mobile crane operator, rigger team on the tower crane, banksman, and HSE supervisor
  • TC condition check before starting — ensuring all screws and pins are still in a condition to be removed safely

A lifting plan for tower crane dismantling work is not a formality document—it is what ensures every lift is safe and the sequence is correct. Read more: What is a Lifting Plan and Why It Is Important


Step 2: Disassemble the Counterweight

This is the first step that must not be skipped.

A counterweight is a large concrete load installed at the end of the counter-jib to balance the load-lifting jib. Its total weight can reach anywhere from over ten to dozens of tons, made up of several individual concrete blocks.

The counterweight must be lowered First before other components are removed, because:

  • If the jib is removed before the counterweight is reduced, the counter-jib will become much heavier than the opposite side—causing extreme imbalance.
  • Lowering the counterweight block by block allows for gradual adjustments to the TC weight distribution

Mobile crane lifts the counterweight blocks one by one from the end of the counter-jib and safely lowers them to the ground.


Step 3: Release and Lower the Jib (Horizontal Boom)

After the counterweight has been completely lowered, the jib can be removed.

The jib is the longest and often the heaviest component to be handled — it can reach a length of 40–70 meters depending on the tower crane type, with a weight of 5–15 tons.

Due to its length, jib almost always requires rigging at two points to prevent bending when lifted. For very long or heavy jibs, this is the moment when tandem lifting Using two mobile cranes is the best choice.

Read more about tandem lifting: Tandem Lifting Crane: Guide and Safe Procedures


Step 4: Release and Lower the Counter-Jib

After the jib is lowered, the counter-jib (the balancing arm on the opposite side) is detached and lowered using a mobile crane.


Langkah 5: Turunkan Cabin Operator

Cabin operator TC yang berada di puncak mast dilepas dan diturunkan ke tanah. Beratnya lebih ringan dibanding jib tapi tetap membutuhkan penanganan yang hati-hati karena bentuknya yang tidak beraturan.


Langkah 6: Lepas Slewing Unit

Slewing unit adalah mekanisme putar yang menghubungkan bagian atas (jib dan counter-jib) dengan mast. Ini adalah komponen yang paling kompleks secara mekanikal.

Setelah slewing unit dilepas, seluruh bagian “kepala” TC sudah diturunkan. Yang tersisa adalah mast yang menjulang vertikal.


Langkah 7: Bongkar Mast Section Per Section (dari Atas ke Bawah)

Ini adalah bagian yang paling memakan waktu dan membutuhkan presisi tertinggi.

Mast terdiri dari section-section yang disambungkan satu per satu saat erection. Saat dismantling, proses ini dibalik — section paling atas dilepas lebih dulu, kemudian section di bawahnya, dan seterusnya hingga tersisa hanya base frame.

Tantangan unik di langkah ini:

  • Setiap kali satu section dilepas, tinggi TC berkurang — mobile crane harus mampu menjangkau titik sambungan yang semakin rendah dengan kapasitas yang tetap memadai
  • Posisi mobile crane mungkin perlu disesuaikan beberapa kali selama proses ini

Langkah 8: Bongkar Base Frame dan Selesai

Tahap terakhir adalah melepas base frame dari ankernya di lantai dan mengangkatnya ke truk pengangkut. Setelah ini, area pondasi TC perlu dirapikan sebelum pekerjaan konstruksi lain bisa dilanjutkan.


Proses Assembling (Erection) Tower Crane

Proses erection adalah kebalikan dari urutan di atas — dimulai dari base frame di bawah, naik ke atas hingga jib dan counterweight.

Proses dismantling tower crane proyek selesai mobile crane bongkar komponen satu per satu

Dismantling tower crane adalah proses kebalikan dari erection — dan sama-sama berisiko tinggi karena melibatkan komponen berat di ketinggian.

Urutan erection:

  1. Pasang dan anchor base frame ke pondasi
  2. Rakit beberapa mast section awal (tinggi awal)
  3. Pasang slewing unit di atas mast
  4. Pasang cabin operator
  5. Pasang counter-jib
  6. Pasang jib
  7. Pasang counterweight bertahap sambil menyeimbangkan distribusi
  8. Climbing — menambah mast section secara bertahap menggunakan climbing frame (proses self-climbing yang unik pada TC)

Proses climbing adalah tahap di mana TC “tumbuh” — menambah ketinggian seiring proyek yang semakin tinggi. Selama fase ini, mobile crane hanya dibutuhkan saat erection awal dan saat ada komponen yang perlu ditambahkan dari luar. Sebagian besar proses climbing dilakukan oleh TC sendiri menggunakan climbing frame hydraulic.


Kapasitas Mobile Crane yang Dibutuhkan

Ini pertanyaan yang paling sering diajukan klien, dan jawabannya sangat tergantung pada tipe dan ukuran tower craneyang akan dipasang atau dibongkar.

Sebagai panduan umum:

Tipe Tower Crane Kapasitas Maks TC Mobile Crane yang Direkomendasikan
TC kecil (proyek residensial) 4–6 ton SANY STC250 / KATO NK300Ev (25–30 ton)
TC menengah (gedung 15–30 lantai) 8–12 ton SANY STC500 (50 ton)
TC besar (gedung 30+ lantai) 12–20 ton SANY STC550 (55 ton)
TC sangat besar / jib panjang > 20 ton komponen Tandem lifting 2 unit 50–55 ton

Yang sering dihitung salah:

Kapasitas mobile crane bukan hanya soal berat komponen TC. Yang lebih kritis adalah kapasitas pada radius kerja dan ketinggian yang dibutuhkan. Mengangkat komponen 8 ton di radius 20 meter ke ketinggian 60 meter membutuhkan crane yang jauh lebih besar dari yang terlihat di atas kertas.

Di proyek Nusa Raya Cipta BSD, ASANINDO menggunakan crane kapasitas 50 ton untuk menangani assembling dan disassembly tower crane di kawasan tersebut — setelah kalkulasi lifting plan yang mempertimbangkan radius aktual, bukan hanya berat komponen.

Untuk memahami kapasitas efektif crane pada berbagai radius dan ketinggian: Sewa Mobile Crane Jakarta: Pilih Kapasitas yang Tepat


Mengapa Ini Bukan Pekerjaan Sembarangan

(Foto operator dan tim lapangan)

Tower crane adalah struktur baja setinggi puluhan meter dengan komponen-komponen yang beratnya mencapai belasan ton — berada di ketinggian yang ekstrem. Jika ada yang salah, konsekuensinya bisa sangat serius.

Risiko nyata yang pernah terjadi di industri:

Ketidakseimbangan saat bongkar Melepas counterweight atau jib dengan urutan yang salah bisa membuat TC kehilangan keseimbangan tiba-tiba. Struktur baja seberat puluhan ton yang kehilangan keseimbangan di ketinggian 50+ meter tidak memberikan banyak waktu untuk koreksi.

Rigging yang tidak tepat Jib yang panjang dan berat membutuhkan rigging di minimal dua titik dengan kalkulasi distribusi berat yang akurat. Rigging yang salah bisa menyebabkan jib melengkung, tergelincir dari kait, atau berayun tak terkendali saat diangkat.

Mobile crane yang salah pilih Menggunakan crane yang kapasitasnya pas-pasan untuk pekerjaan ini berarti crane beroperasi mendekati batas kapasitasnya — kondisi yang meningkatkan risiko secara signifikan.

Koordinasi yang buruk antara tim atas dan bawah Tim yang melepas komponen di atas TC dan operator mobile crane di bawah harus bekerja dengan komunikasi yang sangat jelas dan real-time. Miskomunikasi saat komponen berat sedang menggantung di ketinggian bisa berakibat fatal.


Siapa yang Harus Mengerjakan Pekerjaan Ini?

Berdasarkan pengalaman kami, ada beberapa kriteria yang harus dipenuhi oleh tim yang menangani assembling atau dismantling tower crane:

✅ Mobile crane dengan kapasitas yang benar-benar sesuai Bukan yang “kira-kira cukup” — tapi yang sudah dihitung melalui lifting plan yang akurat berdasarkan data aktual: berat komponen, radius kerja, dan ketinggian angkat.

✅ Operator mobile crane yang berpengalaman dalam pekerjaan TC Ini bukan pekerjaan pertama yang bisa dilakukan begitu saja. Operator harus familiar dengan karakteristik unik angkatan komponen TC — termasuk bagaimana komponen panjang seperti jib bereaksi saat diangkat, dan bagaimana mengontrol ayunan.

✅ Tim rigger dan TC technician yang terlatih Tim yang bekerja di atas TC selama proses bongkar pasang harus memiliki pengalaman khusus — ini bukan pekerjaan rigger biasa. Mereka harus memahami urutan pelepasan komponen dan cara mengamankan setiap komponen sebelum dilepas dari struktur.

✅ Lifting plan yang tertulis dan diverifikasi Dokumen ini harus ada sebelum satu mur pun dilepas. Mencantumkan kalkulasi beban, posisi crane, konfigurasi rigging, dan prosedur jika terjadi kondisi tidak terduga.

✅ Koordinasi komunikasi yang jelas Satu orang yang memiliki otoritas penuh untuk menghentikan seluruh operasi jika ada sesuatu yang tidak sesuai rencana.


Pengalaman ASANINDO dalam Pekerjaan Ini

PT ASANINDO JAYA ABADI telah menangani pekerjaan assembling dan dismantling tower crane di berbagai proyek, termasuk:

  • Nusa Raya Cipta, BSD — assembly dan disassembly TC untuk proyek konstruksi di kawasan BSD City
  • Proyek PIK 2, Jakarta Utara — erection tower crane diselesaikan dalam 1,5 hari berkat koordinasi tim yang baik dan perencanaan yang matang
  • Dan berbagai proyek gedung bertingkat lainnya di Jakarta dan Jabodetabek

Dengan armada mobile crane 25–55 ton dan tim yang sudah familiar dengan prosedur bongkar pasang TC, kami memahami apa yang membuat pekerjaan ini berhasil — dan apa yang harus dihindari.

Lihat dokumentasi proyek nyata ASANINDO: Studi Kasus Proyek Lifting ASANINDO di Jakarta


Pertimbangan Biaya dan Perencanaan

Biaya crane untuk assembling atau dismantling tower crane dipengaruhi oleh:

  • Kapasitas mobile crane yang dibutuhkan — semakin besar TC, semakin besar crane yang diperlukan
  • Durasi pekerjaan — TC kecil bisa selesai dalam 1 hari, TC besar bisa butuh 2–4 hari
  • Jumlah shift — apakah pekerjaan dilakukan dalam jam normal atau perlu malam hari (untuk proyek yang tidak boleh menghentikan akses jalan terlalu lama)
  • Apakah butuh tandem lifting — dua unit crane berarti dua kali biaya unit, tapi sering kali lebih aman dan lebih cepat dari pada satu crane yang bekerja dalam kondisi hampir penuh

Yang kami rekomendasikan:

Lakukan survey bersama tim teknis vendor crane sebelum menentukan anggaran — karena kalkulasi yang tepat di awal jauh lebih murah dari biaya akibat salah pilih crane di hari H.

Untuk melihat harga crane per kapasitas: Harga Sewa Crane Jakarta 2026


Siap Merencanakan Erection atau Dismantling Tower Crane Anda?

PT ASANINDO JAYA ABADI menyediakan mobile crane 25–55 ton dengan operator berpengalaman untuk pekerjaan assembling dan dismantling tower crane di Jakarta dan Jabodetabek.

Setiap pekerjaan TC kami dahului dengan survey lokasi gratis dan penyusunan rekomendasi kapasitas crane yang akurat — bukan perkiraan, tapi kalkulasi berdasarkan data aktual proyek Anda.

Lihat spesifikasi lengkap crane yang tersedia: Rental Crane 55 Ton — Unit Terkuat ASANINDO

📞 Hubungi PT ASANINDO JAYA ABADI via WhatsApp — ceritakan tipe tower crane dan lokasi proyek Anda, kami akan berikan rekomendasi teknis dan penawaran yang akurat.


Artikel ini disusun oleh tim teknis PT ASANINDO JAYA ABADI berdasarkan pengalaman langsung menangani pekerjaan assembling dan dismantling tower crane di berbagai proyek konstruksi di Jakarta dan Jabodetabek. Terakhir diperbarui: Juli 2026.